Work Completed Last Week, September 12th to 16th
·
Completed water service replacements along
Glendale Road
·
Made final connections between new and existing
water mains along Glendale Road
o Water
main work completed for entire project
·
Poured concrete curb & gutter and driveways
along Glendale Road
o Concrete
curb & gutter and driveway replacements completed for entire project
·
Abandoned fire hydrants and valves from old
system
·
Completed minor storm sewer repairs.
·
Adjusted utility structures around jobsite
·
Testing of underground utility improvements
along Ronald Road
·
Graded Glenadale Road in preparation for paving
1st layer of asphalt
Work Anticipated to be completed This week, September 19th
to 23rd
·
Continue with abandonment of fire hydrants and
valves from old system along project site
·
Continue to perform final testing of underground
utilities
·
Continue with utility structure adjustments
along entire project site
·
Fine grading of previously installed topsoil
along Ronald Road
·
Sod installation along Ronald Road
·
Installation and rough grading of topsoil along
Glendale Road
·
Complete fine grading of Glendale Road
·
Pave first layer of asphalt pavement along
Glendale Road, scheduled for Friday, September 23rd.
The majority of underground utility improvements are now
completed for the entire project. The remaining work includes performing final
testing, making minor repairs as needed, and adjusting the structure frames to
the final elevations.
The majority of the concrete curb & gutter and driveway
work is also completed along the project site. A walk-through will be performed
to identify any defects, but any repairs should be minor. Asphalt
driveway restorations are scheduled in the next few weeks as the first layer of
asphalt pavement along Glendale Road is paved.
The contractor will focus on getting the roadway graded for
paving of the first layer of asphalt pavement along Glendale Road. As with the
Ronald Road paving, this will be a significant project milestone that will
allow for a smooth driving surface and greatly reduce the amount of dust on the
project site.
The contractor is also anticipating to perform landscape
restorations by fine grading topsoil and installing sod along Ronald Road and
topsoil installation along Glendale Road.