·
Continued with storm sewer construction
·
Continued water service replacements along
Ronald Road
Work Anticipated to be completed Next week, July 25th
to July 29th
·
Complete storm sewer construction
·
Begin storm sewer service installation
·
Complete water service replacements along Ronald
Road from Greenwood Road to Glendale Road
·
Perform required testing and receive necessary
approvals prior to placing the new water main into service within the second
section of new water main installed along Glendale Road from Ronald Road to
Warren Road.
·
Begin removing existing concrete curb &
gutter along Ronald Road from Greenwood Road to Glendale Road, south side of
roadway.
The contractor will begin removing the concrete curb &
gutter along the SOUTH side of Ronald Road from Greenwood Road to Glendale
Road. During this construction operation, the concrete curb & gutter in
front of each home will be removed. Temporary stone ramps will be installed at
each drive to provide access. The amount of time each resident is restricted
from using their driveway during the removal process should be limited.
It is anticipated the contractor will begin pouring the new
concrete curb & gutter on the south side of Ronald Road from Greenwood Road
to Glendale Road next week as well. During this process, residents will be
restricted from using their driveways for approximately 1 week to allow for the
curb & gutter to be installed and proper curing time of the concrete.
Residents will be able to park on the opposite side of the street during
non-working hours. During working hours, we request you park on adjacent streets
outside the construction zone. Residents will be notified via letter regarding
the day access will be restricted and timeframe for access being restored.
Again this past week, there were several emergency water
shut-downs due to the contractor hitting existing water services while
performing the water service replacements. Unfortunately this is part of
construction. However, please be assured we have had continual discussions
regarding this issue with the contractor and requested great care be taken
while excavating. Should an emergency water shut down need to be performed, we
will notify you as quickly as possible.
Thank you again for all your patience, understanding, and
cooperation as you live within a construction area.