Monday, October 31, 2016

Work Completed!!!

Work Completed
·         Paved surface layer of asphalt pavement
·         Performed walk-through of site to determine any additional areas that needed repair
·         Performed minor repairs identified.

The contractor will continue to monitor the sod to ensure a healthy stand of grass is established.

The major construction work is now completed for the project.

This will be the last Blog Post of the project. We hope that you found the information provided informative and useful. If you have any additional concerns or questions, please contact the Village Project Manager, Chris Gray, at 847-904-435.

Thanks again for all your patience and understanding during the construction project.

Saturday, October 15, 2016

Final Surface Paving Scheduled

Work Completed Last Week, October 10th to 14th  
·         Completed Landscape restoration along Ronald Road and Glendale Road
·         Completed roadway repair near Greenwood Road
·         Performed walk-through with Village, contractor, and engineer
·         Performed minor repairs to improvements that were noted during walk-through with Village, contractor, and engineer
·         Repaired curb & gutter that was identified during walk through with Village, contractor, and engineer
·         Performed televising of newly installed underground utilities
·         Performed repairs identified during internal televising

Work Anticipated to be completed This week, October 17th to 21st
·         Complete all repairs identified.
·         Pave surface layer of asphalt pavement

Following all repairs identified being made, the final layer of asphalt surface will be installed. It is anticipated this work will be completed next week or early the week of October 24th.

Thanks again for all your patience and understanding during the construction process. Hopefully you are beginning to see the of the project and satisfied with the end result.  

Monday, October 3, 2016

Landscape Restoration nearly Completed

Work Completed Last Week, September 26th to 30th   
·         Landscape restoration along Ronald Road and Glendale Road
·         Final testing of underground utilities
·         Adjusting structures to final grade
·         Asphalt driveway restorations
·         Paved first layer of asphalt pavement along Glendale Road
·         Removed and replaced section of roadway that rutted near Greenwood Road
·         Made minor repairs to underground utility improvements 

Work Anticipated to be completed This week, October 3rd to 7th  
·         Complete sod restoration along project site.
·         Complete repair of roadway that rutted near Greenwood Road
·         Complete minor repairs to underground utility improvements
·         Perform final walk-through with Village, contractor, and engineer.
·         Pave surface layer of asphalt pavement

The project is nearing completion.  The first layer of asphalt has been installed along the entire project site. Landscape restoration with new topsoil and sod is nearly completed.

The contractor is continuing to make some minor repairs and adjustments to the underground utility improvements.  Once all repairs are made, a final walk-through will be performed with Village staff, the contractor, and engineering staff to ensure all repairs are completed. 

Following all repairs identified being made, the final layer of asphalt surface will be installed. It is anticipated this work will be completed in the next 1 to 2 weeks.

Thanks again for all your patience and understanding during the construction process. Hopefully you are beginning to see the end of the project and are satisfied with the end result.