Friday, June 24, 2016

Storm Sewer and Sanitary Sewer Work Continues

Work Completed Last Week, June 20th to June 24th  
·         Continued with storm sewer construction
·         Continued with sanitary sewer service replacements

Work Anticipated to be completed Next week, June 27th to July 1st   
·         Continue with storm sewer construction
·         Complete sanitary sewer service replacements
·         Complete required sanitary sewer repairs.
·         Continue to perform required testing and received necessary approvals prior to placing the new water main into service.

 The contractor will continue to work with two crews on-site to complete the storm sewer installation and sanitary sewer service replacements as required.

The contractor is anticipating to complete the necessary sanitary sewer service replacements and sanitary sewer repairs by the end of the next week, prior to the July 4th Holiday.

The contractor is continuing to perform the required testing needed prior to placing the new water main into service and begin replacing the water services to individual homes. They anticipate water service replacements will begin following the July 4th Holiday.

Thanks again for all your patience and understanding.

Friday, June 17, 2016

Storm Sewer Installation and Sanitary Sewer Service Replacements Continue

Work Completed Last Week, June 13th to June 17th  
·         Continued with storm sewer construction
·         Continued with sanitary sewer service replacements
·         Began performing required testing prior to placing the new water main into service

Work Anticipated to be completed Next week, June 20th to June 24th  
·         Continue with storm sewer construction
·         Continue with sanitary sewer service replacements
·         Complete required testing and received necessary approvals prior to placing the new water main into service.

The contractor will continue to work with two crews on-site to complete the storm sewer installation and sanitary sewer service replacements as required.

It is anticipated the contractor will receive the required approvals to place the new water main into service in the next few weeks. Once all the tests have passed and the approvals have been received, the contractor will begin water service replacements to each individual home. They anticipate this work beginning the week of July 27th.

Thank you for all your patience and understanding as you live in a very busy construction site that makes travelling through the neighborhood difficult and dealing with the construction dirt and dust that comes with a project of this size.

Friday, June 10, 2016

Water Main Installation Completed

Work Completed Last Week, June 6th to June 10th
•             Completed water main installation
•             Made connection to existing water main along Greenwood Road
•             Started sanitary sewer replacements

Work Anticipated to be completed Next week, June 13th to June 17th
•             Continue with storm sewer construction
•             Continue with sanitary sewer service replacements
•             Begin performing required testing prior to placing new water main into service.

 The contractor completed the water main installation this week and will begin performing the required tests and necessary approvals for placing the newly installed water main into service. Once all the tests have passed and approvals are received, the contractor will begin replacing the water services to each individual homes.

Next week the contractor will continue replacing sanitary sewer services scheduled to be replaced and installation of the new storm sewer.

Thank you for all your patience and understanding as the construction project continues.

Friday, June 3, 2016

Water Main Continues.

Work Completed Last Week, May 30th to June 3rd
·         Continued with water main installation along Ronald Road and Glendale Road
·         Begin water main construction within cul-de-sacs
·         Directional boring of new water main under Greenwood Road

Work Anticipated to be completed Next week, June 6th to June 10th  
·         Continue with water main installation along Ronald Road and Glendale Road
·         Complete water main within cul-de-sacs
·         Make connection to existing water main along Greenwood Road
·         Start sanitary sewer construction

The contractor started excavating for boring pits and directional boring the new water main and casing under Greenwood Road this week. The intersection of Ronald Road and Greenwood Road was reduced to one lane to facilitate this construction. Everything will be done to open all the lanes as quickly as possible.

The contractor also worked in the intersection of Ronald Road and Glendale Road this week. During this construction, the entire intersection was closed to through traffic.

If all goes as planned, the contractor anticipates having the water main completed by the end of next week. The contractor will then begin performing the required tests and receive the necessary approvals for placing the newly installed water main into service. Once all the tests have passed and approvals are received, the contractor will begin replacing the water services to each individual homes.

The contractor has started, and will continue for the foreseeable future, having 2 crews working on the site. The crews will be working on different aspects of the project. Every effort will be made ensure one lane of traffic is open along Ronald Road and Glendale Road within the various work locations. Should future roadway /intersection closures be required, residents will be notified. You may be requested to use alternate routes to avoid areas of the work zone. Please use caution as you travel through the work zones.

Thank you again for your patience and understanding as you navigate through the various lane and intersection closures along the project site.