Work Completed Last Week, May 30th to June 3rd
·
Continued with water main installation along
Ronald Road and Glendale Road
·
Begin water main construction within cul-de-sacs
·
Directional boring of new water main under
Greenwood Road
Work Anticipated to be completed Next week, June 6th
to June 10th
·
Continue with water main installation along
Ronald Road and Glendale Road
·
Complete water main within cul-de-sacs
·
Make connection to existing water main along
Greenwood Road
·
Start sanitary
sewer construction
The contractor started excavating for boring pits and
directional boring the new water main and casing under Greenwood Road this
week. The intersection of Ronald Road and Greenwood Road was reduced to one
lane to facilitate this construction. Everything will be done to open all the
lanes as quickly as possible.
The contractor also worked in the intersection of Ronald
Road and Glendale Road this week. During this construction, the entire
intersection was closed to through traffic.
If all goes as planned, the contractor anticipates having
the water main completed by the end of next week. The contractor will then
begin performing the required tests and receive the necessary approvals for
placing the newly installed water main into service. Once all the tests have
passed and approvals are received, the contractor will begin replacing the
water services to each individual homes.
The contractor has started, and will continue for the
foreseeable future, having 2 crews working on the site. The crews will be
working on different aspects of the project. Every effort will be made ensure
one lane of traffic is open along Ronald Road and Glendale Road within the
various work locations. Should future roadway /intersection closures be
required, residents will be notified. You may be requested to use alternate
routes to avoid areas of the work zone. Please use caution as you travel
through the work zones.
Thank you again for your patience and understanding as you
navigate through the various lane and intersection closures along the project
site.