Completed grading of aggregate base course in
preparation for paving first lift of asphalt pavement along Ronald Road
·
Received necessary approvals to place the new
water main along Glendale Road from Ronald Road to Warren Road into service.
·
Rough landscape grading and topsoil installation
along Ronald Road behind previously installed curb & gutter
·
Installed first layer of asphalt pavement along
Ronald Road
Work Anticipated to be completed This week, August 29th
to September 2nd
·
Water service replacements along Glendale Road
·
Excavating for concrete curb & gutter
replacement along north side of Glendale Road
·
Depending on work progress, frame and pour
concrete curb & gutter on north side of Glendale Road
·
General site clean-up in preparation for Labor
Day Weekend.
The contractor will begin water service replacements along
Glendale Road this week. Water services will be replaced from the new water
main to the existing valve and box located in front of each home. During the
water service replacement, water to individual homes will be shut-off for
approximately 2-3 hours while the transition from the old service to the new
service is made. The contractor will notify each resident individually
regarding the approximate time and day of the water shut-off prior to turning
off the water.
The contractor is anticipating to begin concrete curb & gutter
and driveway replacements along the north side of Glendale Road this week.
Depending on work progress, the contractor may frame and pour the concrete as
well. During the excavation process, residents will have access to their
driveways at the end of each working day. Once the forming is completed and
concrete is poured, driveway access will be restricted for approximately 5
days. Residents will be notified regarding timing of driveway restrictions via
a letter on your door.