Friday, May 27, 2016

Water Main Continues along Ronald Road and Glendale Road

Work Completed Last Week, May 23rd to May 27th
·         Continued with water main installation along Ronald Road and Glendale Road

 Work Anticipated to be completed Next week, May 30th to June 3rd
·         Continue with water main installation along Ronald Road and Glendale Road moving east.

The contractor was initially scheduled to work within the intersection of Ronald Road and Glendale Road on Tuesday, May 31st. Due to an unforeseen circumstance, this work has been delayed. Additional notifications will be provided regarding the revised schedule of this work.

 Thank you again for your patience and understanding as the water main installation continues.

No work will be performed on-site over the holiday weekend.

Have a safe and fun Memorial Day!!!