Started water service replacements along
Glendale Road
·
Excavated for concrete curb & gutter and
driveway replacement along north side of Glendale Road
·
Installed and rough graded topsoil along Ronald
Road behind previously installed concrete curb & gutter and driveways.
·
General site clean-up in preparation for Labor
Day Weekend.
Work Anticipated to be completed This week, September 5th
to September 9th
·
Complete water service replacements along
Glendale Road
·
Make
final connection between existing water main and new water main near Glendale
Road and Warren Road
·
Abandon
old fire hydrants and valves from old water system
·
Excavate
and form concrete curb & gutter and driveways on south side of Glendale
Road and cul-de-sac
·
Pour
concrete curb & gutter and driveways on south side of Glendale Road and
cul-de-sac
The contractor will complete water service replacements
along Glendale Road this week. Water services will be replaced from the new
water main to the existing valve and box located in front of each home. During
the water service replacement, water to individual homes will be shut-off for
approximately 2-3 hours while the transition from the old service to the new
service is made. The contractor will notify each resident individually
regarding the approximate time and day of the water shut-off prior to turning
off the water.
The final
connection between the old water main and the new water main is also schedule
this week. In order to make this connection, the water will need to be turned
off. The Village of Glenview Water Department will notify those residents
affected by the shut-down the day prior to the work occurring.
Once the water services are completed and the final
connection is made, the underground utility portion of the project will be
completed. The contractor will also begin abandoning the old water system by
removing the old fire hydrants and water valves along the project.
The
contractor has also started preparing for concrete curb & gutter
replacement on the north side of Glendale Road. It is anticipated the concrete
curb & gutter and driveways on the north side of Glendale Road will be completed
by the end of the week.
The contractor will then begin excavating and framing for the curb & gutter on the south side of Glendale Road and cul-de-sac. The concrete curb & gutter and driveway replacement on the south side of Glendale Road, including the cul-de-sac, will be started this week and should be completed early next week.