Completed Landscape restoration along Ronald
Road and Glendale Road
·
Completed roadway repair near Greenwood Road
·
Performed walk-through with Village, contractor,
and engineer
·
Performed minor repairs to improvements that
were noted during walk-through with Village, contractor, and engineer
·
Repaired curb & gutter that was identified
during walk through with Village, contractor, and engineer
·
Performed televising of newly installed
underground utilities
·
Performed repairs identified during internal
televising
Work Anticipated to be completed This week, October 17th
to 21st
·
Complete all repairs identified.
·
Pave surface layer of asphalt pavement
Following all repairs identified being made, the final layer
of asphalt surface will be installed. It is anticipated this work will be
completed next week or early the week of October 24th.
Thanks again for all your patience and understanding during
the construction process. Hopefully you are beginning to see the of the project
and satisfied with the end result.