Continued with storm sewer construction
·
Continued with sanitary sewer service
replacements
·
Began performing required testing prior to
placing the new water main into service
Work Anticipated to be completed Next week, June 20th
to June 24th
·
Continue with storm sewer construction
·
Continue with sanitary sewer service
replacements
·
Complete required testing and received necessary
approvals prior to placing the new water main into service.
The contractor will continue to work with two crews on-site
to complete the storm sewer installation and sanitary sewer service
replacements as required.
It is anticipated the contractor will receive the required
approvals to place the new water main into service in the next few weeks. Once
all the tests have passed and the approvals have been received, the contractor
will begin water service replacements to each individual home. They anticipate
this work beginning the week of July 27th.
Thank you for all your patience and understanding as you
live in a very busy construction site that makes travelling through the
neighborhood difficult and dealing with the construction dirt and dust that
comes with a project of this size.