Friday, June 10, 2016

Water Main Installation Completed

Work Completed Last Week, June 6th to June 10th
•             Completed water main installation
•             Made connection to existing water main along Greenwood Road
•             Started sanitary sewer replacements

Work Anticipated to be completed Next week, June 13th to June 17th
•             Continue with storm sewer construction
•             Continue with sanitary sewer service replacements
•             Begin performing required testing prior to placing new water main into service.

 The contractor completed the water main installation this week and will begin performing the required tests and necessary approvals for placing the newly installed water main into service. Once all the tests have passed and approvals are received, the contractor will begin replacing the water services to each individual homes.

Next week the contractor will continue replacing sanitary sewer services scheduled to be replaced and installation of the new storm sewer.

Thank you for all your patience and understanding as the construction project continues.