Completed water main installation
•
Made connection to existing water main along Greenwood Road
•
Started sanitary sewer replacements
Work Anticipated to be completed Next week, June 13th to
June 17th
•
Continue with storm sewer construction
•
Continue with sanitary sewer service replacements
•
Begin performing required testing prior to placing new water main into service.
Next week the contractor will continue replacing sanitary
sewer services scheduled to be replaced and installation of the new storm
sewer.
Thank you for all your patience and understanding as the
construction project continues.