Completed storm sewer construction along
Glendale Road
·
Completed
storm sewer service installation along Glendale Road
·
Continued
with concrete curb & gutter and driveway replacement on north side of
Ronald Road from Greenwood Road to Glendale Road
·
Continued
with roadway excavation along Ronald Road to Cul-de-sac at Glendale Road.
·
Backfilling behind curb & gutter previously
replaced
Work Anticipated to be completed This week, August 15th
to 19th
·
Complete roadway excavation along Ronald Road
·
Complete
concrete curb & gutter and driveway replacement along Ronald Road
·
Begin
prepping aggregate base course for first layer of asphalt pavement
·
Perform required testing and receive necessary
approvals prior to placing the new water main into service within the second
section of new water main installed along Glendale Road from Ronald Road to
Warren Road.
The concrete work along Ronald Road is anticipated to be
completed by the end of the week. The contractor is also scheduled to complete
the roadway excavation and grading prior to paving the first layer of asphalt
pavement. The first layer of asphalt pavement along Ronald Road from Greenwood
Road to Glendale Road is scheduled to be paved early the week of August 22nd. This will be a major project milestone for
this section of the roadway. Once the first layer of asphalt is paved, a smooth
driving surface will be provided and the amount of dust will be greatly reduced
in this area.